Bridge #312 - CR 42 over Turkey Creek
Current ProjectsLocation: Between CR 21 and SR 15
Designed by: United Consulting
Contractor: RL McCoy
Start Date: 2025
Completion Date: 2025
Estimated Cost: $2,087,311.09
Funded by: 80% Federal, 20% Local
Summary: This bridge, constructed in 1963, is in poor condition due to beam deterioration. The deterioration requires the bridge to be posted with a 24-ton weight limit. For this project, it will be completely replaced with a single-span bridge. The work will require the road to be completely closed during construction, which is expected to take about seven months to complete. The completion date is August 13, 2025.